Major Maintenance FY 2008/2009

Anticipated Summer Schedule


Project Manager:  Roseann Sillasen
Various Contractors

Items Approved 11/30/2007

Work to be performed beginning Spring and Summer 2008

Click here to return to MM2008/2009

Click here to return to the Major Maintenance selection page

Items identified in green signify energy savings measures.

This list is sorted by Building Address and then by Building Number

 

Major Maintenance 08/09 - Work Status
  Location of Work Start Date/Time Finish Date/Time
1 HighRise 4/5 - Aresco 5/27/2008 8/7/2008
2 Schonberg Dance Studio-Aresco 6/18/2008 8/29/2008
3 CAAS Ext Paint - Superior 8/7/2008 8/22/2008
4 Anthropology/281 High - PDI 6/4/2008 7/4/2008
5 Bleak House/287 High - PDI 6/4/2008 7/4/2008
6 35 & 56 Fountain - CSS Morello 6/9/2008 8/15/2008
7 Neighborhood Day care - CSS Morello 5/20/2008 6/14/2008
8 64 Fountain Reno - CSS Morello 6/6/2008 8/20/2008
9 2 Fountain - CSS Morello 6/9/2008 6/20/2008
10 Butterfield B Kitchen - Brown & Wimler 5/27/2008 8/20/2008
11 200 High Bsmt Shower - Brown & Wimler 5/27/2008 6/24/2008
12 CAAS Carpet - Olson Flooring 6/2/2008 7/10/2008
13 HighRise Asphalt Ramp - Jim Stamm 8/19/2008 8/19/2008
14 Butterfield C210/C312 - Babbidge 8/4/2008 8/15/2008
15 CAAS Lounge - Babbidge 6/23/2008 7/18/2008
16 CAAS 134 - Classroom Reno - Cobalt Construction 6/11/2008 7/8/2008
17 PAC 136 - Classroom Reno - Cobalt Construction 7/9/2008 7/18/2008
18 CFH 106 - Classroom Reno - Cobalt Construction 7/21/2008 7/29/2008
19 318 High St - Superior Finishes 6/5/2008 6/19/2008
20 DAC Entry - Canning 6/6/2008 7/11/2008
21 23 A&B Vine & 7 Vine - Olson Flooring 6/9/2008 6/23/2008
22 VVO Windows - Brown & Wimler 6/9/2008 8/22/2008
23 CAMS/255 High St - Sifco 6/16/2008 8/1/2008
24 GLSP/284 High - Superior Finishes 6/18/2008 7/31/2008
25 WSA/109 High - RestTech 6/16/2008 7/17/2008
26 330 High - PDI 6/16/2008 7/27/2008
27 258 Court - Superior Finishes 6/16/2008 8/22/2008
28 159 High Windows - Brown & Wimler 6/23/2008 8/22/2008
29 15 Fountain Ave Roof Replacement - CSS Morello 6/7/2008 6/8/2008
30 51 Fountain - Porch Replace - CSS Morello 6/26/2008 8/15/2008
31 40 Fountain Floor Replace - CSS Morello 6/27/2008 8/15/2008
32 43 Fountain Floor Replace - CSS Morello 6/27/2008 8/15/2008
33 57 Fountain Floor Replace - CSS Morello 6/27/2008 8/15/2008
34 2, 6, 7, 57 Fountain - Paint Porches - CSS Morello 6/27/2008 8/15/2008
35 269 Pine St Chimney Repointing - CSS Morello 6/30/2008 7/7/2008
36 215 A & B Pine St Porch Replacement - CSS Morello. 6/23/2008 7/21/2008
37 40, 42 Fountain - Kitchen Reno - CSS Morello 5/27/2008 8/15/2008
38 211 Pine St Porch Replacement - CSS Morello 6/23/2008 7/21/2008
39 22 Lawn Ave Chimney Repoint - CSS Morello 7/21/2008 8/4/2008
40 10 A & B Fountain - Window Replace/Ext Paint - CSS Morello 6/18/2008 8/1/2008
41 35 Fountain Ave - Porch & Window Replacement / Paint- CSS Morello 6/30/2008 8/4/2008
42 40 Fountain Ave - Window Replace/Ext Paint - CSS Morello 6/25/2008 8/15/2008
43 42 Fountain - Window Replace/Ext Paint - CSS Morello 6/25/2008 8/22/2008
44 56 Fountain - Window Replace/Vinyl Siding/Floor Place 6/2/2008 8/20/2008
45 41 Fountain- Porch Replace/Paint - CSS Morello 6/23/2008 8/8/2008
46 Russell House/350 High - Sifco 6/23/2008 8/1/2008
47 Eclectic - Superior Finishes 7/7/2008 8/22/2008
48 Public Safety/208 High - RestTech 7/10/2008 8/8/2008
49 171 Church - Superior Finishes 7/15/2008 8/22/2008
50 167169 High - Superior Finishes 7/21/2008 8/15/2008
51 163 High - Superior Finishes 7/23/2008 8/18/2008
52 159 High - Superior Finishes 7/28/2008 8/22/2008
53 Fisk Hall Fire Escapes - PDI 8/4/2008 8/29/2008
54 Zilkha Roofing - Allied Restoration 7/14/2008 8/15/2008
55 Foss Hill 2 Roofing - Allied Restoration 7/28/2008 8/8/2008
56 105 Cross St Roof Replacement - Parady 7/17/2008 7/21/2008
57 24 Fountain Ave Roof Replacement - Affordable Home Repair 8/1/2008 8/20/2008
58 6 Fountain Ave Roof Replacement - Macri Roofing 6/20/2008 6/20/2008
59 86 Lawn Ave Roof Replacement - Parady 7/21/2008 8/1/2008
60 131 Mt Vernon Roof Replacement - Macri 6/30/2008 7/4/2008
61 152 Mt Vernon Roof Replacement - Affordable Home Repair 6/17/2008 7/8/2008
62 163 Mt Vernon Roof Replacement - Parady 7/7/2008 7/16/2008
63 170 Mt Vernon Roof Replacement - Affordable Home Repair 6/10/2008 8/8/2008
64 207 Pine St Roof Replacement - Silktown Roofing 6/16/2008 7/15/2008
65 211 Pine St Roof Replacement -Affordable Home repair 6/16/2008 8/8/2008
66 329 Washington Terr - Affordable Home Repair 6/30/2008 8/8/2008
67 136 High Street Roof Replacement - ??? 7/21/2008 7/30/2008
68 65 Pearl -Roof Replacement - Affordable Home Repair 8/21/2008 9/5/2008
69 125 Mt Vernon Ext Paint - Nutmeg 8/28/2008 9/26/2008
70 130 Mt Vernon Ext Paint - Sifco 8/18/2008 9/18/2008
71 131 Mt Vernon Ext Paint - Nutmeg 8/4/2008 9/8/2008
72 134 Mt Vernon Ext Paint - Superior 9/26/2008 10/17/2008
73 135 Mt Vernon Ext Paint - Nutmeg 8/29/2008 8/29/2008
74 146 Mt Vernon Ext Paint - PDI 9/15/2008 10/17/2008
75 152 Mt Vernon Ext Paint - Superior 9/18/2008 10/17/2008
76 158 Mt Vernon Ext Paint - Sifco 8/11/2008 9/12/2008
77 163 Mt Vernon Ext Paint - Sifco 6/13/2008 8/15/2008
78 164 Mt Vernon Ext Paint - Superior 8/26/2008 9/18/2008
79 170 Mt Vernon Ext Paint - Superior 8/21/2008 9/18/2008
80 319 Washington Terr Ext Paint - Goodco 6/23/2008 7/25/2008
81 329 Washington Terr Ext Paint - PDI 9/15/2008 10/17/2008
82 200 Church Street ADA Entrance 8/29/2008 10/17/2008
83 Squash Building - Exterior Paint - Sifco 8/4/2008 8/9/2008
84 258 Court Street - Replace storm windows - CSS Morello 8/1/2008 8/29/2008
85 South College Flag Pole - Superior 7/2/2008 7/4/2008
86 170 Mt Vernon Stucco Repairs - CSS Morello 8/20/2008 8/22/2008
87 190 High - WSA - Porch replacments - CSS Morello 6/27/2008 7/17/2008
88 CFA Zilkha 2nd Floor - Budget Estimate for New office 6/26/2008 7/26/2008
89 Park Washington Window replacement bid package 8/25/2008 9/5/2008
90 Woodframe Window Replacements 8/18/2008 8/29/2008
91 Freeman Athletic Ctr East Elevation wood replacement - CSS Morello 7/31/2008 8/22/2008
92 Zilkha Gallery Window Shade costing 6/23/2008 7/26/2008
93 Neon Deli Ext Paint 8/18/2008 9/8/2008
94 Butterfield A window replacement - R&R 8/14/2008 8/15/2008
95 High Street Sidewalk Replacement - west side DAC to Wyllys 8/13/2008 8/26/2008
96 Cross Street Sidewalk Replacement - south sideWarren to Pine 7/6/2009 7/17/2009
97 PAC Roof Investigation to address leaks 8/27/2008 8/29/2008