Major Maintenance 2008/2009

Approved Project Bid Packages

Contact Roseann Sillasen

 

The following are bid packages that will be put out to bid.

 

Bid Package # Sequence Number Building Name Building Address Project Name Short Description Out to Bid
1 B020 Student WF 15 Fountain Ave Replace porch roof Replace main and porch roofs.  1/22/2008
1 B028 Student WF 51 Fountain Ave Exterior wood siding repair / Porch replacements Exterior wood siding repair. Replace front and rear porches. 1/22/2008
1 B034 Student WF 40,43,57 Fountain Ave Bathroom floor replacements Replace damaged sheet vinyl flooring with VCT. Remove and install new plywood subfloor. 1/22/2008
1 B035 Student WF 2,6,7,57 Fountain Ave Paint porch decks, rails, stairs Paint porch decks, rails, stairs, columns, ceilings as identified 1/22/2008
1 B039 Student WF 269 Pine St Chimney Repair Repoint exposed portion of chimney. Remove top 8 courses and reinstall. 1/22/2008
1 B043 Student WF 215 A&B Pine St Replace front porch and rear entry stairs/landing Demo existing front porch and replace with composite material. Demo concrete stairs and landings at rear entry and replace with composite material.  1/22/2008
1 B047 Student WF 40,42 Fountain Ave Kitchen Renovations Total gut of existing kitchen. Replace kitchen cabinets, sink, appliances. Address electric, fire alarm, steam radiator.  1/22/2008
1 B049 Student WF 35, 56 Fountain Ave Kitchen/common area floor replacements Flooring is damaged beyond repair leaving poor quality living quarters for students,  Install new subfloor. 1/23/2008
1 B050 Student WF 64 Fountain Ave Paint or Vinyl Side Exterior & Replace Windows Prep and paint exterior & replace windows. Paint all paintable surfaces. Carpentry repair. 1/22/2008
1 B056 Student WF 211 Pine St Egress Stairs Replace rear egress concrete stairs and landings. Install new code compliant egress with composite materials. 1/22/2008
1 B057 Student WF 22 Lawn Ave Repoint Chimney Repoint existing chimney. Remove antenna. 1/22/2008
1 B059 Student WF 64 Fountain Ave Reno 6 Bed House (Existing 2 family 3/3 conversion to single family) Renovation of existing house. Plank construction. Install 3/8" GWB over existing walls. Channel in new conduit prior to installation of of GWB.  Reno kitchen and bathrooms. Relocate entry door to bedroom from kitchen to living room. Relocate walls to provide better sized bedrooms. Eliminate 2nd floor kitchen, install closet. Install additional outlets in kitchen, bedrooms and common areas.  Replace fin tube radiators with new. Add indirect hot water heater to existing DeDietrich boiler. Insulate all plumbing water supplies against outside walls, in crawl space and at hatchway. 1/22/2008
1 B063 Student WF 10/12 Fountain Ave Exterior Reno & Replace Windows  Repair exterior stucco. Replace windows. Wrap exterior windows trim with aluminum. Paint all paintable surfaces. Install new gutter and leaders, replace rear porches. Infill existing covered east window openings to match stucco finish. 1/22/2008
1 B064 Student WF 35 Fountain Ave Replace Windows  / Porch replacement Replace windows. Paint all paintable surfaces. Demo and construct new front and rear porches. 1/22/2008
1 B065 Student WF 40 Fountain Ave Paint or Vinyl Side Exterior & Replace Windows  Paint exterior. Replace windows. Paint all paintable surfaces. Reepair stucco.  Infill west covered window opening to match stucco finish. 1/22/2008
1 B066 Student WF 42 Fountain Ave Reno Exterior & Replace Windows/ Replace Roof Paint exterior. Replace windows. Paint all paintable surfaces. Perform stucco repairs.  Address porches. 1/22/2008
1 B067 Student WF 56 Fountain Ave Paint or Vinyl Side Exterior & Replace Windows Paint or Vinyl Side Exterior & Replace Windows. Provide costs for both options. 1/22/2008
1 B071 Student WF 41 Fountain Gutters/Rear Porch/Painting Install gutters.  Replace rear porch railing system with new. Remove and replace asphalt covered section with new. Provide new footings, framing, and enclosed area. 1/22/2008
  Click here to view the list of General Contractors bidding Bid Package #1. - Package Awarded to CSS Morello
             
2 B024 Student WF 23B Vine St Kitchen & Bathroom floor replacement Replacement of bathroom and kitchen floors and refinishing of wood common area floor 

2/1492008

2 B031 Student WF 23A Vine St Bathroom floor replacement Replace bathroom floor to include subfloor. Install new subfloor and sheet vinyl. Install base. Trim bottom of door. 2/19/2008
2 B055 Student WF 7 Vine St New carpet installation Remove entry and living room carpet. Inpect wood floor for possible refinish.  install new vct or walk off mat flooring at entry. 2/19/2008
2 B069 CAAS 343 High St Foyer and stair carpet replacement Replace carpeting in foyer on main floor common areas and stairs. 2/19/2008
  Click here to view the bid package
             
3A B036 Van Vleck Observatory 11 Foss Hill Dr Window Replacement Replace all windows and provide window treatment, blinds etc. Design by Noyes Vogt Architects.

2/28/2008

3A B072 Student WF Earth House - 159 High St Window Replacement Replace windows thorughout house. Maintain existing trim. Insulate pockets.

2/28/2008

  Click here to view list of General Contractors
   
3B B060 Butterfield A 25 Lawn Ave Window Replacement Replace all windows in dormitory. Design by Noyes Vogt Architects.  
 
   
3C B048 Butterfield A 25 Lawn Ave Stairtower door replacements/Paint Scrape and paint exterior surfaces, Replace all exterior wood doors frames with new metal doors and frames. Install new panic hardware.  
 
             
4 B038 Non-Traditional Dorm / Program House Eclectic - 200 High St Ground Floor Bathroom Renovation Renovate Ground Fl. Bathroom.  Currently servicing 4 Bedrooms.  Install new floor, new ACT tiles, shower unit, new toilet, paint, and proper exhaust.

2/28/2008

4 B076 Butterfield B 20 Huber Ave New kitchen in Lounge Provide common area kitchen space for student use. Build secured space in lounge. Also address shelving replacement, lighting, finishes, sprinkler, electrical, HVAC.

2/28/2008

  Click here to view list of General Contractors
             
5 B003 High Rise 110 Church St Building security Add 2nd card access door beyond laundry room 1/22/2008
5 B005 High Rise 110 Church St Door Upgrades Replace west entrance door and install vestibule door. 1/22/2008
5 B054 High Rise 110 Church St 4th and 5th floor renovation Renovate Kitchens and bathrooms in each apartment on the 4th and 5th floors. Total renovations include kitchens & bathrooms same scope as upper floors in High Rise, replace base molding throughout and paint entire unit (ceilings included). Replace hallway carpeting, paint corridor walls/ceilings, replace common area lighting and common area emergency lighting and replace smoke detectors. Demo closet in existing 2-bed units and install new ceiling lighting in common area. Install wall hung counters to eliminate kitchen tables. Replace all sprinkler heads in units with new quick response heads. Replace all ceiling lighting. Install new wall switches for all new lighting installed. Replace all smoke detectors with new. Replace existing t-stats with lite-stats. Install access panels and shut offs for all supplies in chase in bathrooms and kitchens. Provide strapping and anchorage for fin tube radiation. 1/22/2008
  Contact Rob Schmidt for list. - Package Awarded to Aresco Construction
             
6 B073 Univ. Relations & Alum 318 High St Paint Exterior / carpentry repair Paint exterior in its entirety including metal railings and metal ramp at north elevation. Treat exterior mold. 2/21/2008
6 B124 CAMS 255 High St Paint Exterior / carpentry repair Prep exterior clapboard and paint the exterior of the building.  2/21/2008
   
             
7 B077 Non-Traditional Dorm / Program House 200 Church St Install security card access control system Install security card access control system. Perform door repairs and provide sufficient card access for front, rear, side and fire escape doors.    
   
             
8 Exec Neighborhood Pre School 20 Lawn Ave Vinyl Side Exterior Vinyl Side exterior of house, remove all lead paint.

2/19/2008

  Click here to view bid package
             
9 B016 Graduate 258 Court St Paint exterior, replace porches Paint entire exterior of house.  Repair front and back porches and columns. Carpentry work.   
   
             
10 B0177 Davison Art Center 301 High St Loading Dock Door Replacement Replace double doors at loading dock to match entry door. New installation must be able to provide clear opening of double doors. Requires carpentry work to existing trim, frame, threshold.  
   
   
11 B300-01 Earth House 159 High Street Exterior Painting  

2/21/2008

11 B300-02 Russian House 163 High Street Exterior Painting  

2/21/2008

11 B300-03 Community Relations / Chaplains Office 167/169 High Street Exterior Painting  

2/21/2008

11 B300-04 Religious Studies 171 Church Street Exterior Painting  

2/21/2008

11 B300-05 WSA 190 High Street Exterior Painting  

2/21/2008

11 B300-06 Eclectic 200 High Street Exterior Painting  

2/21/2008

11 B300-07 Public Safety 208 High Street Exterior Painting  

2/21/2008

11 B300-08 Anthropology 281 High Street Exterior Painting  

2/21/2008

11 B300-09 GLSP 284 High Street Exterior Painting  

2/21/2008

11 B300-10 Bleak House 287 High Street Exterior Painting  

2/21/2008

11 B300-11 Alumni Office 330 High Street Exterior Painting  

2/21/2008

11 B300-12 CAAS/Malcolm X 343 High Street Exterior Painting  

2/21/2008

11
B300-13
Russell House 350 High Street Exterior Painting  

2/21/2008

  Click here for Bid Invitation and Drawing List