General Contractor 2 walk held on 3/16/17

Addendum #1 dated 3/23/17.

Locations addressed in this addendum:

  • Pre-bid conference notes
  • South College Connector 1st Floor connector Replacement/2nd Floor Window Replacement
  • CFA G Art Studio South Ne Aluminum Storefront and Doors to Room 105
  • Foss Hill 1-10 New Bathroom Cubbies

General Contractor 2 walk held on 3/16/17

-Addendum #2 dated 3/27/17.

- General Contractor Bid Proposal Form 3/27/2017

Locations addressed in this addendum:

___________________________________________________________________________________________________________________

___________________________________________________________________________________________________________________

General Contractor walk held on 3/15/17

Addendum #1 dated 3/24/17.

Locations addressed in this addendum:

  • Pre-bid conference notes
  • 71 Lawn Ave, Vinyl Siding / Window Replacement Project
  • 161 Cross Street – Freeman Athletic Center Natatorium Hockey Rink Exterior Repairs
  • 200 High Street Building 1st Floor Selective Structural Reinforcing
  • 45 Wyllys – Stair Base Treatment at Usdan

General Contractor walk held on 3/15/17

Addendum #2 dated 3/29/17.

Locations addressed in this addendum:

- General Contractor Bid Proposal Form 3/27/2017

___________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________

Site Contractor walk held on 3/17/17

-Addendum #1 dated 3/27/17.

-Sitework Contractor Bid Proposal Form 3/27/17

Locations addressed in this addendum:

Site Contractor walk held on 3/17/2017

Addendum #2 dated 3/29/17.

Locations addressed in this addendum:

  •  318 High Street North Ramp Replacement

Site Contractor walk held on 3/17/2017

Addendum #3 dated 4/3/17

   Revised Proposal Form Dated 4/3/2017

________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________

Roofing Contractor walks held on 3/13/17 and 3/15/17

Addendum #1 dated 3/27/17.

- Hall Atwater Loading Dock Proposal Form dated 3/27/17.

Olin Library Bid Form dated 3/27/17.

Locations addressed in this addendum:

Roofing Contractor walks held on 3/13/17 and 3/15/17

 Addendum #2 dated 3/29/17.

Locations addressed in this addendum:

  • Olin Library
  • Hall Atwater

Roofing Contractor walks held on 3/13/17 and 3/15/17

 Addendum #3 dated 3/30/17.

Locations addressed in this addendum:

Roofing Contractor walks held on 3/13/17 and 3/15/17

 Addendum #4 dated 3/30/17.

Locations addressed in this addendum:

Roofing Contractor walks held on 3/13/17 and 3/15/17

 Addendum #5 dated 3/31/17.

___________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________

Fire Alarm Contractor walks held on 3/16/17 

Addendum #1 dated 3/28/17.

- Fire Alarm Contractor Bid Proposal Form 3/28/17

Locations addressed in this addendum:

  • Pre-bid conference notes
  • HighRise

Fire Alarm Contractor walks held on 3/16/17 

Addendum #2 dated 3/30/17.

Location addressed in this addendum:

  • HighRise

Fire Alarm Contractor walks held on 3/16/17 

Addendum #3 dated 4/11/17.

Location addressed in this addendum:

  • HighRise