Major Maintenance FY 24

This page is updated frequently.

Project Manager:  Joseph Banks

             Wesleyan University is committed to sustainability and environmental stewardship. 
          Emphasis has been placed on waste reduction, recycling, environmentally preferable purchasing,
          energy conservation and the use of materials that are either harvested through sustainable
methods or made from recyclable materials.
 
 

                                 2023 Summer Construction Location Map  (interactive)

 

                                 ___________________________________________________________________________________________________________________

Work performed and completed Summer 2022

      Capital & MM FY23 Projects - Construction Completed Summer 2022

___________________________________________________________________________________________________________________

__________________________________________________________________________________________________________________

Lien Waiver Links:

         -Partial lien waiver
         -Final lien waiver
___________________________________________________________________________________________________________________
The following work has been approved to be performed the summer 2023.Please search the list for your building’s name or address and for any abutting buildings within proximity to your building to remain informed of work being performed and forecasted on campus. Capital projects and additional work will be identified as it is approved.
Building Name Building Address Project name Managed by
Student WF

Campus wide - 32 Brainerd, 57 Brainerd, 81 Home, 122 Knowles, 55 Lawn, 9/11 Brainerd, 148 Church, 258 Court , 1 Long Lane, 5 Long Lane, 152 Mt Vernon,146 Mt Vernon, 12 Fairview 

Structural repairs JBB
Foss Hill 5.5 Foss Hill Drive Bedroom floor replacement AS
Undergrad WF - Farm House  344 Washington Street Interior renovations JBB/SF
Vine St Parking Lot Stairs Knowles Avenue Replace stairs from parking lot to Knowles Ave VD/SF
Center for African American Studies 343 Washington Terrace Copy room floor repair, carpet replacement MJC
CFA P Theater 271 Washington Terrace Rigging repairs ASW/JBB
92 theater 213 High Street Rigging repairs ASW/JBB
CFA B Crowell Concert Hall 50 Wyllys Avenue Rigging repairs ASW/JBB
Malcolm X / Center for African American Studies 345 High Street Paint exterior MBH/SF
CFA Ring Family Performing Arts Hall 287 Washington Terrace Entrance JBB/MR
Freeman Athletic Center - Boathouse 35 Harbor Park Exterior and drainage repairs JBB
Landscape - 95 Pearl 95 Pearl Street Repairs to brownstone wall VD/SF
North College 237 High Street Elevator Modernization MBH/MC
Memorial Chapel 221 High Street Dehumidification JBB
Olin Library 252 Church Street Repair window seals on large window in 1986 Addition JBB
CFA Theater 271 Washington Terrace Loading dock/Drainage JBB
Freeman Athletic Center 161 Cross Street Replace basketball roof top units MBH/MC/JBB
Center for African American Studies 345 High Street Continue 2nd floor office finishes MJC/TP
Olin Library 252 Church Street New carpet - Reserve Desk, Access Service Office, Interlibrary Loan Office, Reference Desk Area MJC
CFA H Art Studio South 271 Washington Terrace Site Drainage JBB/MR
Russell House 350 High Street 2nd floor office finishes MJC
Undergrad WF 63 Pearl Street Interior and Exterior renovations SF/JBB/ASW
Foss Hill 5 Foss Hill Dr Bedroom floor replacement AS
Undergrad WF 115 A Cross Street Interior Renovations SF/JBB
Freeman Athletic Center 161 Cross Street Reno Men's General Locker Room JBB / ASW
CFA Ring Family Performing Arts Hall 287 Washington Terrace HVAC replacements, lighting JBB
Butterfield 25 Lawn Avenue Landscape Improvements VD
Undergrad WF 57 Fountain Avenue Interior and exterior renovations SF/JBB
Foss Hill 8-9 McConaughy Dr Design to replace walkway roof JBB
Student WF 63 Fountain Avenue Interior renovation  JBB/ASW/SF
Russell House 350 High Street 2nd Floor bathroom renovations MJC/MBH
Usdan - PAC High Street Replace west elevation walk VD/JBB

 ________________________________________________________________________________________________________________ 


AP=Andrew Plotkin aplotkin@wesleyan.edu
AR=Alan Rubacha arubacha@wesleyan.edu
AS=Andres Sarda asarda@wesleyan.edu
ASW=Angela Wong aswong@wesleyan.edu
BH=Brandi Hood bhood@wesleyan.edu
CC=Chris Cruz ccruz01@wesleyan.edu
JS=Jeff Sweet jsweet@wesleyan.edu
JBB=Joe Banks jbanks01@wesleyan.edu
JB=Josh Blodgett jblodgett@wesleyan.edu
MJC=Melinda Campbell mcampbell02@wesleyan.edu 
MC=Mike Conte mconte@wesleyan.edu
MBH=Marco Hahn mhahn@wesleyan.edu 
MR=Mike Rosalie mrosalie@wesleyan.edu
RZP=Rhucha Parab rparab@wesleyan.edu
SF= Steve Formica sformica@wesleyan.edu 
TP=Tom Policki tpolicki@wesleyan.edu
VD=Victor Diaz vdiaz01@wesleyan.edu

ACAD=Academic    Admin=Administrative    Infra=Infrastructure    RP=Rental Properties    SLF=Student Life Facilities   SLF-WF=Student Life Facilities-Woodframes     ATH=Athletics   CPP=Central Power Plant    AAF=Academic & Administrative Affairs    MH=Manhole    DDC=Direct Digital Controls    GFI=Ground Fault Interrupt   SW=southwest    ADA=Americans with Disabilities Act   CFA=Center for the Arts