Project Name / Description |
Building Name |
Building Address |
Managed by |
Work Schedule |
Paint exterior of house and addition in toto. Perform carpentry repairs as identified.
|
Program House
|
Gingerbread House - 202 Washington St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Demolish existing and construct new first floor front porch. Paint west and southwest egress stair systems. Install new windows on 1st and 2nd floor.
|
Student WF
|
261 Pine St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Paint exterior of house. Paint all paintable surfaces. Perform carpentry repair.
|
Student WF
|
57 Fountain Ave
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Perform carpentry repairs to front porch, railings and wood siding as identified. Provide new porch stairs and footing. Provide Code compliant intermediate railing. Paint house and all paintable surfaces. |
Program House |
Asian / Asian American - 107 High St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Annual funds to replace failed boiler / furnaces
|
Student WF / Traditional Non-traditional Dorms / Program
|
Campus wide
|
Mike Conte
|
May 24, 2010 - July 31, 2010
|
Annual funds to replace failed appliances.
|
Student WF / Traditional Non-traditional Dorms / Program
|
Campus wide
|
Mike Conte
|
May 24, 2010 - July 31, 2010
|
Demolish and construct new east elevation 1st floor porch. Replace windows; vinyl side exterior; paint areas of trim/porch windows as identified. |
Student WF |
251 Pine St - 2 Family |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Replace windows and repair concrete header on second floor above windows on east elevation. Address interior window trim as required. Wrap exterior stops. |
Student WF |
211 Pine St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Perform masonry repairs to east entry bluestone patio and all stairs from street level to upper level main entry.
|
PAC
|
238 Church St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
South Exit Doors: Replace doors, hardware, and weatherstripping.
|
Freeman Athletic Center-Bacon Field House
|
161 Cross St
|
Sean Higgins / Jeff Sweet / R Sillasen
|
May 24, 2010 - July 31, 2010
|
Paint all paintable exterior surfaces. Perform carpentry repairs as noted and identified. |
Student WF |
7 Fountain Ave |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Four sets Dbl. doors to lockers
|
Freeman Athletic Center-Hockey Area
|
161 Cross St
|
Sean Higgins / Jeff Sweet / R Sillasen
|
May 24, 2010 - July 31, 2010
|
|
Butterfield A |
Lawn Ave |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Replace east exit doors (3) and hardware in Hockey area. Replace north double door to corridor and hardware, replace door and hardware to women's entrance, replace door, frame and hardware to mechanical room.
|
Freeman Athletic Center-Hockey Area
|
161 Cross St
|
Sean Higgins / Jeff Sweet / R Sillasen
|
May 24, 2010 - July 31, 2010
|
Replace southeast exit doors, frame, and hardware in Bacon Field House.
|
Freeman Athletic Center - Bacon Field House
|
161 Cross St
|
Sean Higgins / Jeff Sweet / R Sillasen
|
May 24, 2010 - July 31, 2010
|
Provide metal roof repairs to stop leaks and paint large dome.
|
Van Vleck Observatory
|
11 Foss Hill Dr
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Remove all carpet in student rooms, refinish wood floors.
|
Student WF / Non-Traditional Dorm / Program House
|
Bayit - 157 Church St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Repair theatrical lighting system. Existing electrical cabling is very old. Insulation on conductors are dry, brittle and cracking. |
CFA P - Theater |
283 Washington Terr |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Perform repairs to exterior concrete stairs. Spalling from exposed rebar. Prep surfaces, treat rebar and coat surfaces with DiamondKote surface treatment. Install new handrails to be ADA compliant. |
CFA M - Zilkha |
283 Washington Terr |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Existing 3 bed house requires interior renovation to address kitchen, bathroom, finishes, electrical and plumbing. Update fire alarm. |
Student WF |
2 Warren St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Remove existing front and rear wood/glass doors and replace with new metal doors and frames.
|
Student WF
|
2 Warren St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Perform repairs to exterior concrete stairs at north entrance. Spalling from exposed rebar. Prep surfaces, treat rebar and coat surfaces with DiamondKote surface treatment. Install new handrails to be ADA compliant. |
CFA C - World Music |
283 Washington Terr |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Annual contingency to address floor finishes in need of replacement in all student occupied housing.
|
Student WF, Non-Traditional Dorm / Program House
|
Campus wide
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Install emergency lighting in ceilings in penthouse, 7th, 6th and 5th floors of science center.
|
Exley Science Center
|
265 Church St
|
Mike Conte
|
May 24, 2010 - July 31, 2010
|
Exterior tree and landscape clearing around buildings and woodframes. |
Residential areas |
Campus Wide |
Dave Hall
|
May 24, 2010 - July 31, 2010
|
Vine St Transformer Distribution 09/10-Replacement of electrical feeders to bring COGEN to Vine St |
Campus Wide |
Campus wide |
Alan Rubacha
|
May 24, 2010 - July 31, 2010
|
Install new security card access control system |
Non-Traditional Dorm |
156 High St |
Rob Schmidt
|
May 24, 2010 - July 31, 2010
|
Existing interior stone stair treads in south stairtower are worn. Infill worn treads with epoxy type material and cover with rubber dot non-slip stair treads and risers.
|
North College
|
237 High St
|
Roseann Sillasen / Tom Policki
|
May 24, 2010 - July 31, 2010
|
Demo existing retaining wall in southwest section of yard on sidewalk side of house. Regrade, install new retaining wall.
|
Student WF
|
86 Lawn Ave
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
At main entrance on Cross Street, replace exterior doors, hardware, and swap vestibule and exterior; new hardware weatherstrip
|
Freeman Athletic Center
|
161 Cross St
|
Sean Higgins / Jeff Sweet / R Sillasen
|
May 24, 2010 - July 31, 2010
|
Reno 3 bed house to create a 4th bedroom on the 2nd floor in existing kitchen. Demo 1st floor bathroom. Reno 2nd floor bathroom. |
Student WF |
269 Pine Av |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Install code compliant speaker notification fire alarm devices in all areas, including stacks; add smoke detectors as necessary. |
Olin Library |
252 Church St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Small dome is showing signs of age. Inspect metal roof, repair and necessary and paint.
|
Van Vleck Observatory
|
12 Foss Hill Dr
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
|
|
|
|
May 24, 2010 - July 31, 2010
|
Electrical/mechanical upgrades/repairs as identified. |
Rental Properties |
Campus wide |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Paint exterior. Repair wood soffits and wood details as identified. |
Student WF |
267 Court St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Upgrade existing elevator controllers of the two bank elevator in the north lobby. |
Exley Science Center |
265 Church St |
Mike Conte
|
May 24, 2010 - July 31, 2010
|
Upgrade EMS controls. Remove and replace 9 pneumatic control valves serving FCU with electronic type. Provide automated logic ZN551 zone controller for each zone. Replace existing pneumatic t-stats with electronic sensors. Control 6 sections of perimeter radiation. Run new communication wiring and tie in to existing ARCnet 156K communication network. Furnish and install new VFD for pump PL1. Reinsulate pipes.
|
CFA L - Art Workshops |
283 Washington Terr |
Mark Chadsey
|
May 24, 2010 - July 31, 2010
|
Replace windows and repair and paint front and rear porches. 3 units
|
Student WF
|
65 Pearl
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Reno kitchen, patch and paint interior, insulate, install new hardware, screen wood floors. Upgrade elect./ replace mech. systems. Reno 2nd floor full bathroom. |
Program House |
Earth House - 159 High |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Stain exterior, paint all paintable surfaces. Perform carpentry repairs. |
Student WF |
15 Fountain Ave |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Inspect and repair/replace bridge panel motors. Motors leak oil. |
CFA P - Theater |
283 Washington Terr |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Perform repairs to existing wood siding, stain, waterproof. Remove, make watertight and reinstall windows on this elevation. Reflash coping on roof above this area. |
Freeman Athletic Center - Hockey Rink / Corridor areaway |
161 Cross St |
Jeff Sweet / Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Repair/patch EFIS. Paint all paintable exterior surfaces including the EFIS surfaces. Initiate work at the northeast elevations. Soffits beginning to deteriorate. |
Freeman Athletic Center |
161 Cross St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Create 2 new bedrooms by partitioning common rooms. 1st floor kitchen renovation. 2nd floor kitchen demo to study/library. Demo 2nd floor shared wall between common room and hallway. Address electrical, sprinkler and fire alarm affected by new walls and demolished areas. |
Program House |
65 Lawn - German Haus |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Reno existing 5 bedroom house. Review structural needs. Address electrical/plumbing. Reuse fire alarm system/sprinkler. |
Student WF |
134 Cross St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Clean existing siding. Install vinyl shutters on south elevation. |
Student WF |
128 Church St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Replace concrete walk on West side of Mt Vernon St . Transition into house walkways, stairs and driveways. Obtain approval from private home owners.
|
Mt Vernon St - west side |
Mt Vernon St |
Roseann Sillasen / Dave Hall
|
May 24, 2010 - July 31, 2010
|
Paint exterior. Address exterior carpentry items.
|
Student WF
|
73 A&B Lawn Ave
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Clean duct work in facility. |
Butterfield A/B |
Lawn/Huber Ave |
Mike Conte
|
May 24, 2010 - July 31, 2010
|
Paint front and rear porches. Minor carpentry. |
Student WF |
235 Pine St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Paint fire escape at north elevation. Paint east and west exterior doors and railings on lower levels.
|
Shanklin
|
237 Church St
|
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Minor stucco repair northwest corner of house. Replace side porch with new stoop, railings and stair per code. Patch stucco and paint where enclosed porch was removed. Install new basement door and trim back trees. |
Student WF |
131 Cross St |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Renovate interior to create additional bedrooms. Address electrical/plumbing. Kitchen and bathroom renovations. New fire alarm/sprinkler system. New windows. Paint exterior paintable surfaces. |
Program House |
44 Brainard Ave - Womanist House |
Roseann Sillasen
|
May 24, 2010 - July 2, 2010
|
Minor renovation to create new bedroom. Address electrical, fire alarm and sprinkler. |
Student WF |
56 Fountain Ave |
Roseann Sillasen
|
May 24, 2010 - July 31, 2010
|
Carpentry repairs, gutter/leader replacement, exterior painting |
Program House |
250 Court St |
Roseann Sillasen |
May 24, 2010 - July 31, 2010 |