Location
|
Estimated Start Date
|
Estimated Completion
|
Punch List Completion Date
|
Priority items Managed by Roseann Sillasen x3476
|
|
|
|
Lowrise B Interior Maintenance Fire Alarm installation complete 6/10. Electrical, bathroom plumbing and wall patching in progress.
|
5/24/04
|
7/30/04
|
9/3/04
|
|
|
|
|
Lowrise B Water Main Installation for Fire Sprinkler System Excavation work to begin at Church St down Hotchkiss to Building B for new water main w/o 7/5. Sprinkler piping 37% complete. |
6/21/04 |
6/25/04 |
9/3/04 |
|
|
|
|
Foss #4 High Voltage Oil Fuse Change OutPower outage scheduled 6/17 & 6/18
|
6/14/04
|
6/18/04
|
6/19/04
|
|
|
|
|
Foss #5 High Voltage Oil Fuse Change OutPower outage scheduled 6/10 & 6/11
|
6/7/04
|
6/11/04
|
6/12/04
|
|
|
|
|
107 High Street Roof Replacement Roof complete. Pending gutter installation.
|
6/18/04
|
6/24/04
|
7/14/04
|
|
|
|
|
151 Church Street Roof Replacement
|
TBD
|
TBD
|
8/30/04
|
|
|
|
|
128 Pearl Street Rain Leader Connection to City Storm Sewer System Regrading required.
|
6/1/04
|
6/2/04
|
6/30/04
|
|
|
|
|
Butterfield Cooling Tower Replacement All air conditioning supply is required to be shutdown for this work to occur. System drain down 7/9. Demolition of cooling tower 7/12. Steel erection begins 7/14.
|
7/8/04
|
8/6/04
|
9/22/04
|
|
|
|
|
230 Washington Street Boiler ReplacementAbatement completed 6/8/04. Room firesafed. New boiler in process of being built.
|
6/7/04
|
7/23/04
|
8/30/04
|
|
|
|
|
Freeman Strainer/Valves Grodsky Mechanical to perform work. Eros Pools to assist with pool draining and water circulation during shutdown.
|
8/9/04
|
8/20/04
|
8/20/04
|
|
|
|
|
Freeman Track Repair By Dalton Bubbling areas to be cut and resecured to surface. Steeplechase pit slice to be repaired.
|
7/12/04
|
7/14/04
|
7/27/04
|
|
|
|
|
Vine Street Tennis Courts 9-16 By Dalton
|
7/1/04
|
7/5/04
|
7/27/04
|
|
|
|
|
163 High Street Window & Floor Replacement/ Wall Repairs Demo complete, new ceilings installed. Subfloor for new flooring in progress. Fire Alarm complete. Windows to be installed w/o 7/26.
|
5/24/04
|
8/6/04
|
8/25/04
|
|
|
|
|
163 High Street Water Main Installation For Fire Sprinkler System. Sprinkler installation on going.
|
6/7/04 |
7/9/04 |
8/25/04 |
|
|
|
|
34 Lawn Avenue Kitchen MaintenanceAbatement performed 6/1-6/4. Floor installationcomplete. Electrical in progress. Cabinet installation in progress. Window to be installed w/o 7/26.
|
5/31/04
|
8/6/04
|
8/15/04
|
|
|
|
|
34 Lawn Avenue Exterior Painting Exterior power wash performed 6/7/04. Painting in progress beginning w/o 6/21/04.
|
6/18/04
|
6/30/04
|
9/27/04 pending storm window
|
|
|
|
|
170 College Street Bathroom & Window Repairs Demo complete. New walls installed. Subfloor installed. Shower unit installed.
|
5/31/04
|
7/12/04
|
8/7/04
|
|
|
|
|
Park Washington Elevator Pump ReplacementOtis Elevator to perform work.
|
7/6/04
|
7/9/04
|
7/11/04
|
|
|
|
|
154 Church Street Roof Replacement In progress by Eagle Roofing. Gutters pending.
|
6/28/04
|
7/2/04
|
8/30/04
|
|
|
|
|
30 Fountain Avenue Windows/ Porches Porch rebuilds complete. Painting to be performed. Windows to be installed w/o 7/26.
|
5/24/04
|
8/6/04
|
8/15/04
|
|
|
|
|
125 Mt Vernon Electrical Client meeting 6/18.Electrical work in progress. Work may continue with house occupied.
|
6/24/04
8/17/04
|
7/2/04
8/27/04
|
8/15/04
|
|
|
|
|
125 Mt Vernon Roof Replacement 7:00 am start time. To be completed 7/2. Gutter work pending.
|
6/24/04
|
7/2/04
|
8/15/04
|
|
|
|
|
135 Mt Vernon Electrical Upgrade Electrical work completed. Final patch and paint in progress.
|
5/25/04
|
6/28/04
|
8/15/04
|
|
|
|
|
10 Brainerd Avenue Roof Replacement Rake edge to be completed. Gutter work pending
|
6/7/04
|
7/6/04
|
8/15/04
|
|
|
|
|
130 Mt Vernon Roof Replacement 8:00 am start time. Gutter work pending.
|
6/24/04
|
7/7/04
|
8/15/04
|
|
|
|
|
146 Cross Street Porch Roof Replacement In progress. Gutter work pending.
|
6/24/04
|
7/9/04
|
8/1/04
|
|
|
|
|
146 Cross Street Porch Repair Gutter work pending
|
5/24/04
|
7/6/04
|
8/1/04
|
|
|
|
|
146 High Street Roof Replacement Gutter work pending.
|
6/11/04
|
7/7/04
|
8/1/04
|
|
|
|
|
268 Court Street Roof Replacement Issues obtaining terra cotta shingle color.
|
6/28/04
|
7/1/04 TBD
|
8/15/04
|
|
|
|
|
258 Court Street Roof Replacement Perform masonry work to chimneys prior to roofing replacement
|
6/28/04
|
7/12/04
|
8/30/04
|
|
|
|
|
162 Cross Street Exterior Paint
|
7/19
|
7/2304
|
8/20/04
|
|
|
|
|
65 Lawn Avenue Exterior Paint
|
6/28/04
|
7/9/04
|
8/30/04
|
|
|
|
|
PAC Elevator Controller ModernizationThyssen Elevator on site. |
6/28/04 Elevator out of service |
7/16/04 |
7/21/04 |
|
|
|
|
Science Tower Areaway Repair (Lawn Avenue) This is a noise producing project. Hammer drilling, sawing, diamond cutting into concrete walls. Waterproofing in progress |
6/2/04 |
7/18/04 |
8/30/04 |
|
|
|
|
CFA Music Studios Elevator Cylinder & Pump Replacement Final inspection by elevator inspection. |
5/24/04 |
6/18/04 |
6/20/04 |
|
|
|
|
VVO Roof Replacement Crane, dumpsters and tar pot to be placed on North side of building. Non-toxic fumes will be generated during this work. |
6/28/04 |
7/2/04 |
8/5/04 |
|
|
|
|
|
|
|
|
Priority items Managed by Barbara Spalding x3780 |
|
|
|
202 Washington Street Fire Alarm & Sprinkler Upgrade In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
316 Washington Street Fire Alarm Upgrade and New Sprinkler System In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
65 Pearl Street Fire Alarm Upgrade and New Sprinkler System In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
1 Vine Street Fire Alarm Upgrade and New Sprinkler System In progress |
5/24/04 |
7/30/04 |
8/30/04 |
|
|
|
|
230 Washington Street Fire Alarm & Sprinkler Upgrade In progress |
5/24/04 |
7/30/04 |
9/30/04 |