Major Maintenance Construction Schedule

Return to Major Maintenance FY 04/05 Priority List 

Location

Estimated Start Date

Estimated Completion

Punch List Completion Date

Priority items Managed by Roseann Sillasen x3476

 

 

 

Lowrise B Interior Maintenance Fire Alarm installation complete 6/10. Electrical, bathroom plumbing and wall patching in progress.

5/24/04

7/30/04

 9/3/04

Lowrise B Water Main Installation for Fire Sprinkler System Excavation work to begin at Church St down Hotchkiss to Building B for new water main w/o 7/5. Sprinkler piping 37% complete. 6/21/04 6/25/04 9/3/04

 

 

 

 

Foss #4 High Voltage Oil Fuse Change OutPower outage scheduled 6/17 & 6/18

6/14/04

6/18/04

 6/19/04

 

 

 

 

Foss #5 High Voltage Oil Fuse Change OutPower outage scheduled 6/10 & 6/11

6/7/04

6/11/04

 6/12/04

 

 

 

 

107 High Street Roof Replacement Roof complete. Pending gutter installation.

6/18/04

6/24/04

 7/14/04

 

 

 

 

151 Church Street Roof Replacement

TBD

TBD

 8/30/04

 

 

 

 

128 Pearl Street Rain Leader Connection to City Storm Sewer System Regrading required.

6/1/04

6/2/04

6/30/04

 

 

 

 

Butterfield Cooling Tower Replacement  All air conditioning supply is required to be shutdown for this work to occur. System drain down 7/9. Demolition of cooling tower 7/12. Steel erection begins 7/14.

7/8/04

8/6/04

 9/22/04

 

 

 

 

230 Washington Street Boiler ReplacementAbatement completed 6/8/04. Room firesafed. New boiler in process of being built.

6/7/04

7/23/04

 8/30/04

 

 

 

 

Freeman Strainer/Valves Grodsky Mechanical to perform work. Eros Pools to assist with pool draining and water circulation during shutdown.

8/9/04

8/20/04

 8/20/04

 

 

 

 

Freeman Track Repair By Dalton Bubbling areas to be cut and resecured to surface. Steeplechase pit slice to be repaired.

7/12/04

7/14/04

 7/27/04

 

 

 

 

Vine Street Tennis Courts 9-16 By Dalton

7/1/04

7/5/04

 7/27/04

 

 

 

 

163 High Street Window & Floor Replacement/ Wall Repairs Demo complete, new ceilings installed. Subfloor for new flooring in progress. Fire Alarm complete.  Windows to be installed w/o 7/26.

5/24/04

8/6/04

 8/25/04

163 High Street Water Main Installation For Fire Sprinkler System. Sprinkler installation on going.

6/7/04 7/9/04 8/25/04

 

 

 

 

34 Lawn Avenue Kitchen MaintenanceAbatement performed 6/1-6/4. Floor installationcomplete. Electrical in progress. Cabinet installation in progress. Window to be installed w/o 7/26.

5/31/04

8/6/04

8/15/04

 

 

 

 

34 Lawn Avenue Exterior Painting Exterior power wash performed 6/7/04. Painting in progress beginning w/o 6/21/04.

6/18/04

6/30/04

 9/27/04 pending storm window

 

 

 

 

170 College Street Bathroom & Window Repairs Demo complete. New walls installed. Subfloor installed. Shower unit installed.

5/31/04

7/12/04

 8/7/04

 

 

 

 

Park Washington Elevator Pump ReplacementOtis Elevator to perform work.

7/6/04

7/9/04

 7/11/04

 

 

 

 

154 Church Street Roof Replacement In progress by Eagle Roofing. Gutters pending.

6/28/04

7/2/04

 8/30/04

 

 

 

 

30 Fountain Avenue Windows/ Porches Porch rebuilds complete. Painting to be performed. Windows to be installed w/o 7/26.

5/24/04

8/6/04

 8/15/04

 

 

 

 

125 Mt Vernon Electrical Client meeting 6/18.Electrical work in progress. Work may continue with house occupied.

6/24/04

 8/17/04

7/2/04

8/27/04

 8/15/04

 

 

 

 

125 Mt Vernon Roof Replacement 7:00 am start time. To be completed 7/2. Gutter work pending.

6/24/04

7/2/04

 8/15/04

 

 

 

 

135 Mt Vernon Electrical Upgrade Electrical work completed. Final patch and paint in progress.

5/25/04

6/28/04

 8/15/04

 

 

 

 

10 Brainerd Avenue Roof Replacement Rake edge to be completed. Gutter work pending

6/7/04

7/6/04

 8/15/04

 

 

 

 

130 Mt Vernon Roof Replacement 8:00 am start time. Gutter work pending.

6/24/04

7/7/04

  8/15/04

 

 

 

 

146 Cross Street Porch Roof Replacement In progress. Gutter work pending.

6/24/04

7/9/04

 8/1/04

 

 

 

 

146 Cross Street Porch Repair Gutter work pending

5/24/04

7/6/04

  8/1/04

 

 

 

 

146 High Street Roof Replacement Gutter work pending.

6/11/04

7/7/04

  8/1/04

 

 

 

 

268 Court Street Roof Replacement Issues obtaining terra cotta shingle color.

6/28/04

7/1/04 TBD

  8/15/04

 

 

 

 

258 Court Street Roof Replacement Perform masonry work to chimneys prior to roofing replacement

6/28/04

7/12/04

 8/30/04

 

 

 

 

162 Cross Street Exterior Paint

7/19

7/2304

 8/20/04

 

 

 

 

65 Lawn Avenue Exterior Paint

6/28/04

7/9/04

 8/30/04

PAC Elevator Controller ModernizationThyssen Elevator on site. 6/28/04 Elevator out of service 7/16/04 7/21/04
Science Tower Areaway Repair (Lawn Avenue) This is a noise producing project. Hammer drilling, sawing, diamond cutting into concrete walls. Waterproofing in progress 6/2/04 7/18/04 8/30/04
CFA Music Studios Elevator Cylinder & Pump Replacement Final inspection by elevator inspection. 5/24/04 6/18/04 6/20/04
VVO Roof Replacement Crane, dumpsters and tar pot to be placed on North side of building. Non-toxic fumes will be generated during this work. 6/28/04 7/2/04 8/5/04
Priority items Managed by Barbara Spalding x3780
202 Washington Street Fire Alarm & Sprinkler Upgrade In progress 5/24/04 7/30/04 8/30/04
316 Washington Street Fire Alarm Upgrade and New Sprinkler System In progress 5/24/04 7/30/04 8/30/04
65 Pearl Street Fire Alarm Upgrade and New Sprinkler System In progress 5/24/04 7/30/04 8/30/04
1 Vine Street Fire Alarm Upgrade and New Sprinkler System In progress 5/24/04 7/30/04 8/30/04
230 Washington Street Fire Alarm & Sprinkler Upgrade In progress 5/24/04 7/30/04 9/30/04

Last Updated 9/23/04