Major Maintenance FY 2017
Project Manager:  Roseann Sillasen


Locations and Scope of Work Subject to Change-

It is the Viewer's Responsibility to Check Back Frequently

for the Most Current Information

 

Wesleyan University is committed to sustainability and environmental stewardship.  Emphasis has been placed on waste reduction, recycling,

environmentally preferable purchasing, energy conservation and the use of materials that are either harvested through sustainable methods or

made from recyclable materials.

  Historical Information for work performed MM FY16

The following link provides before and after photographs of MM FY16 work approved and completed Summer 2015:

Major Maintenance Slide Show -Completed projects FY16

 

Photo diary of approved major maintenance priority items for FY17:

MM FY17 Approved Priority Photo List


If you have difficulty opening the links in Internet Explorer, please use Modzilla FireFox. Thank you.

 

 

4-14-2016 Bid Info Box

Davison Health Center Windows, 284 High Street Water Infiltration Repairs, Fire Escape Repairs

Bids are due 4/25/16 at 11:00 am.  Bids may be emailed.

ADDENDUM A dated 4/19/16

 

Proposal Form 4/14/16

Davison Health Center Window Replacement 4/14/16

Window shade contact: Al Bruckner - alpha.aero@snet.net

Davison Health Center Photos/existing drawings

Retroaire Fan coil unit cut sheets   &   Enclosure (for reference/coordination)

 

284 High Street water infiltraiton repairs 3/14/16

 

Fire Escape: Additional Information for clarification

Fisk Hall 4/14/16

South College 4/14/16

200 Church Street 4/14/16

190 High Street 4/14/16

200 High Street 4/14/16

THE FOLLOWING DOCUMENTS ARE A PART OF THE FIRE ESCAPE REPAIR CONTRACT

Fire Escape Structural Assessement Report (Reference for complete scope of work)

200 Church St Fire Escapes - Existing Drawings

South College Fire Escape - Existing Drawings

200 High St Fire Escape - Existing Drawings

262 High Street (Fisk Hall) Fire Escapes - Existing Drawings

Addendum #1 dated 3/6/16

Addendum #2 dated 3/22/16

 

 

 



Proposal Forms and Material Reference Sheets posted 3/19/16

General Contractor Project Scopes Bid Form:     Area 1 - 2 -3 - 4 - 5 - 6

Site Contractor Project Scopes Bid Form:           Area 7

Roofing Contractor Project Scopes Bid Form:     Area 8

Interior Material Reference Sheet

Exterior Material Reference Sheet

Mechanical and Electrical Material Reference Sheet

Typical Stair Details Reference Sheet

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AREA #4 INFO BOX  

Contractor Sign In Sheet                                                            

  Addendum #1 dated 3/5/16

  300 High St Fire Escape Report/Scope

  330 High St Interior Window Soffit

 Addendum #2 dated 3/16/16   

Addendum #2 - Davison Health Center Bid Documents dated 3/11/16      

Addendum #3 dated 3/21/16    

 Addendum #4 dated 3/23/16

Addendum #5 dated 3/23/16

AREA #6 INFO BOX                                                       

Contractor Sign In Sheet

Addendum #1 dated 3/6/16

Fire Escape Structural Assessement Report

200 Church St Fire Escapes - Existing Drawings

South College Fire Escape - Existing Drawings

200 High St Fire Escape - Existing Drawings

262 High Street (Fisk Hall) Fire Escapes - Existing Drawings

Addendum #2 dated 3/22/16

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

AREA #7 INFO BOX      

Contractor Sign In Sheet    

Addendum #1 dated 3/15/16                                               

Addendum #1 - VVO Bid Documents dated 3/15/16                            

                               

                                                   

AREA #1 INFO BOX

Contractor Sign In Sheet                                          

Addendum #1 dated 3/15/16

Addendum #1 - 214 High Street Porch Schematic-revised in Addendum #3

Addendum #1 - 151 Church Street Exterior Fire Escape Scope of Work dated 3/18/16          

Addendum # 2 dated 3/21/16

Addendum #3 dated 3/23/16

Addendum #3 - 214 High Street Porch revised 2nd floor stair

                    

AREA #2 INFO BOX

Contractor Sign In Sheet

Addendum #1 dated 3/15/16

Addendum #1 - 113 Cross St Fire Alarm Layout

Addendum #1 - 9 Vine Street Interior Scope

                                                                                                 

AREA #3 INFO BOX

Contractor Sign In Sheet

Addendum #1 dated 3/15/16

                                                                                      

  

 

 

 

 

 

 

 

 

 

 

  

 

 

 

AREA #5 INFO BOX                                                               

Contractor Sign In Sheet    

Addendum #1 dated 3/17/16   

Addendum #1 - VVO Bid Documents dated 3/15/16

Addendum #1 - VVO door hold open device dated 3/17/16

Addendum #1 - Russell House Floor Plan dated 3/17/16

Addendum #2 - Russell House Basement Carpet

                                                                                                  

AREA #8 INFO BOX                                                    

Contractor Sign In Sheet

Addendum 1 dated 3/11/16

Addendum #2 dated 3/16/16

Addendum #3 dated 3/22/16

Addendum #4 dated 3/23/16

                                                                                      

 

 

 

 

 

THE FOLLOWING IS A LIST OF WORK THAT WILL BE COMPLETED SUMMER 2016. SCOPES WILL BE UPDATED AS THEY BECOME AVAILABLE.

BIDDING IS BY INVITATION. CONTACT Roseann Sillasen WITH YOUR INTEREST TO BID.

 

Project Specifications for all projects: - UPLOADED 3/23/16

    MM FY16 Project Manual Divisions 0-1

    MM FY16 Project Manual Divisions 2 - 16

    MM FY16 Project Specifications: Attachments, Exhibits, Stair Detail - Part of the Project Manual

Sample partial lien waiver

Sample final lien waiver

Hazardous Material Reports by Location; uploaded 3/21/2016:

9 Vine St, 16 Jackson St, 22 Lawn Ave, 37 Home Ave, 49 Home Ave, 55 Home Ave, 73 A & B Home Ave, 82 Lawn Ave, 110 Mt Vernon St, 113 Cross St, 151 Church St, 154 Church St, 167/169 High St, 214 High St, 223 Pine St, 230 Washington St, 235 Pine St, 240 Court St, 258 Court St, 330 High St, Alsop House (301 High St), Davison Health Center (327 High St), Romance Languages (300 High St)Russell House (350 High St)


PROPOSED MAINTENANCE

BUILDING NAME

BUILDING ADDRESS

BUILDING USE

MANAGED BY

 START/

COMPLETION

PHOTOS/SCOPE

AWARDED CONTRACTOR

Install new heating system. Design required Center for the Americas 255 High St ACAD MC/RZS      MJ Emonds
Water infiltration in the basement from the entry patio at the foundation wall of the addition. Downspout penetrates bluestone patio in this corner. Investigate and develop options for repair, and proceed with the work. Patio removal and restoration will be required. Admissions 70 Wyllys Ave ADM RZS  RESOLVED IN HOUSE    
Area 5: Water infiltration in the basement from the north elevation. Repair plaster walls in basement kitchen, replace window sills. Scrape and paint interior stone wall in mechanical room. College of the Environment 284 High St ACAD RZS May 30, 2016

 Photos

 Raccio Construction

Area 1: Install new insulated glass windows. Reinforce south exterior stair tower/apply wood preservative and stain and remove lattice panels-provide intermediate ballusters; replace north elevation entry porch. New basement bilco hatch. Remove abandoned water heater. Address water infiltration.

Renovate 1st, 2nd and 3rd floor bathrooms. New kitchen and laundry room flooring. Wall repairs. Finish all floors. Paint entire interior.

Non-Traditional Dorm / Program House 151 Church - International House - 12 beds SLF RZS  May 25, 2016

 Photos

Scope

 Robison Construction
Area 4: Upgrade mechanical system in clinic areas. Replace framed steel windows/exhaust diffusers with new insulated glass window to match existing style. Provide insert with exhaust requirements for new fan coil units. (Design Drawings in Progress) Davison Health Center 327 High St ADM RZS/MC   May 25, 2016

 Photos & Existing

Condition Drawings

Noyes Vogt Architects - Design

G. Donovan - Window Renovation

MJ Emonds - Fan Coil Units

Obtain engineering design for the replacement of steam and condensate in the tunnel from North College to Fisk Hall. North College to Fisk Hall High St ATH AR    Photos  TBD

Area 1: Remove existing stucco exterior and install new stucco system, carpentry work, foundation repointing. Partial window replacement

Alternate Finish: Exterior Finish Insulation System

Annex 16 Jackson St ACAD RZS   May 1, 2016

 Photos

Scope

 Superior Finishes
Replace asphalt right of way behind Park Washington from Park Ave to High Street. Provide traffic calming. Replace parking area for 230 Washington Street. Provide ADA space when restriping. Non-Traditional Dorm / Program House Gingerbread House - 202 Washington St SLF RB  

 Photos

Bid/Scope Package

 Carpenter Construction
Provide new hot water system, new piping as required. Malcolm X 343 High Street SLF MC  May 24, 2016   Trane
Area 1: Install new insulated windows (except in kitchen), insulate window pockets. Install vinyl siding; match architectural detail, intermediate banding and changes in horizontal side heights. Interior window trim -paint completely. Wrap exterior window trim with sheet metal, new gutters and leaders. Roof Replacement. Student WF 22 Lawn Ave - 5 beds SLF-WF RZS   May 25, 2016

Photos

Scope

 

CSS Morello

Area 3: Vinyl side exterior. Install new insulated glass windows. Wrap window trim with rolled metal. Paint interior window trim completely. paint exterior paintable surfaces.

Replace existing mechanical systems and provide a single boiler with appropriate BTU to serve both units. Provide additional heating zones and network thermostats. Convert to hot water system, wall hung condensing units with new perimeter baseboard.

Student WF 73 A/B Lawn Ave - 6 beds SLF-WF RZS    May 25, 2016

 Photos

Scope

 Signature Construction Group
Provide design services for the replacement of all windows at HighRise.  Hazardous material testing and invasive investigation required. Water proof building exterior prior to window replacement.
HighRise 110 Church St SLF RZS    May 24, 2016    Design Pending
Install control valves on individual fan coil units. Clark Hall  268 Church St SLF MC  June 19, 2016 - availability varies. Compl by Aug 19, 2016    TBD
Area 3: Kitchen and bathroom renovations, mechanical system upgrades, electrical upgrade, paint all surfaces of interior, floor finishes, carpentry. Demolish rear entry enclosure, construct new landing and shed roof at rear entry. New insulated glass windows; wrap exterior trim with rolled metal. Vinyl side exterior. Paint exterior paintable surfaces. Student WF 37 Home Ave SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Area 2: Clean, stain and varnish kitchen cabinets. Remove carpeting and install vinyl plank floors-2nd floor. Prep and paint wall finishes, paint entire interior. Minor 1st floor bathroom renovation/new flooring (2). Inspect electrical for required upgrades, new light fixtures, investigate and perform mechanical upgrades,  Install new insulated glass windows; wrap window trim with rolled metal. Install vinyl siding. East and south elevation porch replacements. . Student WF 9 Vine St  SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Kitchen renovation. Paint front porch railings and columns. Replace rear deck system with new composite materails. Faculty/Staff 33 Brainerd RP RZS  March 2016 - coordinated with occupant    CSS Morello
Area 1: Reside exterior of building with cementitious siding. Maintain architectural features. Tongue and groove decking replacement on High Street elevation.  Install new windows on 2nd floor. Prep and paint all paintable surfaces. Replace south elevation entry ADA ramp. Roof repairs.
167/169 High St 167/169 High St ACAD/ADM RZS May 25, 2016

Photos

Scope

 Signature Construction Group

Area 7: Water infiltration and damage to southeast elevation of basement wall. Excavate, install drainage system and regrade east and south elevations.

Area 4: Remove and repair deterioriated window trim, mostly north & east side. Wood consolidation also to be performed.
Remove carpet, and floor system in ground floor southwest corner office. Pour concrete floor, Interior wall repair and paint office. Install new carpet tiles and perimeter trim.

Romance Languages 300 High St ACAD RZS  May 25, 2016

 Photos

Scope

 Superior Finishes
Replace all exterior glass entry doors with Aluminum framed doors with piano hinges. Install automatic door openers. Usdan Campus Center 45 Wyllys Ave ACAD TP/AR    May 25, 2016

 Photos

 Advanced Performance Glass
Area 3: Kitchen and bathroom renovations, mechanical system upgrades, electrical upgrade, new walls, insulation,  complete interior paint, floor finishes and refinishing, carpentry.  Student WF 55 Home Ave SLF-WF RZS    May 25, 2016

 Photos

Scope

 The Rockfall Company
Install new heating system. Maintain existing cast iron radiators and cut pipes so radiators sit properly on the floor. Convert to hot water system.  Non-Traditional Dorm / Program House 200 Church St SFL MC/RZS June 1, 2016    TBD - Design Phase
Area 4: Vinyl side exterior. Carpentry repairs. Gutters/leaders. Remove shed on north elevation and patch area. GLSP 74 Wyllys SLF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Area 2: Install vinyl siding over existing cedar shades. Wrap exterior trim with rolled metal. Student WF 12 Warren St - 5 bed house SLF-WF RZS    May 25, 2016

 Photos

Scope

 The Rockfall Company
Area 4: Replace east porch. Install new windows on original house. Paint interior trim. Metal wrap exterior window trim. Paint entire exterior, includes addition. 230 Washington 230 Washington SLF RZS    May 25, 2016

 Photos

Scope

 Superior Finishes
Demolish garage; regrade, place top soil, seed. Student WF 27 Brainerd Ave-garage SLF-WF RZS    May 25, 2016

 Photos

 The Rockfall Company
Area 2: Interior paint-complete, floor finishes/refinishing, carpentry. New insulated glass windows. New porches.  Wrap exterior window trim. Paint exposed exterior surfaces. Student WF 235 Pine St SLF-WF RZS    May 25, 2016

 Photos

Scope

 Signature Construction Group
Area 4: Repair/patch/paint walls in offices and hallways.  Install new windows and replace window blinds. Install vinyl siding. Replace roof. Install central cooling system to eliminate window a/c units. High profile location. Require design for central cooling system. Univ. Relations & Alum 330 High St ADM RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Heating system upgrade – Install electronic power transformers on each unit. Malcolm X 343 High Street ACAD MC    May 25, 2016   TBD
Area 4: Vinyl side exterior.  Remove west exterior entry door to Apt 2 and install knee wall and new window.  New insulated glass windows. New exterior stair systems at apt 1 and apt 7. Install hardware on kitchen door at apartment 7. Abate transite siding. DVD Zone.  Student WF 240 Court St SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Replace asphalt from High Street entrance to Church Street entrance. Address drainage. Line parking spaces and address ADA requirements.   Non-Traditional Dorm / Program House 156 High St SLF RB    May 25, 2016

 Photos

Scope/Bid Package

 Superior Finishes

Area 5:

Replace carpeting in main entrance

Replace carpet on the second floor landing and adjacent corridor requires abatement

Replace carpeting on stairs leading to basement level and basement entry corridor.  Abatement required.

Russell House 350 High St ACAD RZS    May 25, 2016  Photos/Scope  GA Olson & Sons
Area 3: Kitchen and bathroom renovations, mechanical system maintenance, electrical upgrade, replace east  porch decking with composite. Vinyl siding and paint exterior paintable surfaces. Student WF 49 Home Ave SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Demo garage. Regrade, top soil, seed. Student WF 63 Pearl Place SLF-WF RZS    May 25, 2016

 Photos

 TBD

Campus landscape renewal projects-restore existing locations.  

Campus landscape renewal projects- moderate restoration of Butterfield Courtyard

Grounds Campus wide INFRA RB

 

Butterfield Bid/Scope Package

 Photos-

Photos-Butterfield

 
Replace existing mechanical systems and provide a single boiler with appropriate BTU to serve both units. Provide additional heating zones and network thermostats. Convert to hot water system, wall hung condensing units with new perimeter baseboard Student WF 59 A/B  Home Ave SLF-WF MC    May 25, 2016  TBD

Area 1: Paint entire interior. Replace kitchen counter tops, perform all related plumbing work requirements. Screen floors. Remove abandoned oil tank.

Repoint all elevations of brick facade. Replace south elevation porch. Carpentry repair to soffit. Provide new replicated shutter missing on south elevation. Paint all paintable exterior surfaces.   Replace basement hatch with metal bilco and provide hardware. Install railing on north entry landing. DVD Zone.

Minor roof replacement on east elevation bay window.

Non-Traditional Dorm / Program House 154 Church St - Open House - 7 beds SLF RZS    May 25, 2016

 Photos

Scope

 Signature Construction Group
Area 1: Vinyl side exterior/maintain architectural details, intermediate band boards, decorative siding, fir out and wrap window trim, replace east and west porches with composite materials. Non-Traditional Dorm / Program House 159 High St - Earth House - 11 beds SLF RZS    May 25, 2016

Photos

Scope

 

Superior Finishes

Area 3: House is vinyl sided. Paint exterior paintable surfaces. Removing exisitng wood decking, columns, stairs and install new composite porch decking, new composite porch stair systems, railings, lattice, horizontal and vertical running boards, columns. Student WF 27 Brainerd Ave SLF-WF RZS    May 25, 2016

 Photos

Scope

 The Rockfall Company
Area 2: Renovate kitchen and bathrooms. Electrical upgrades, new lighting throughout. Paint entire interior. Refinish floors. Fire Alarm system. Student WF 113 Cross S t - 4 beds SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Repair garage, new garage doors. Garage 162 Church St SLF-WF RZS    May 25, 2016  Photo/Scope  Superior Finishes
Area 5: Abate ACT in all bedrooms and replace with new VCT and vinyl base. 26 bedrooms Foss Hill Unit 3 Foss Hill Dr SLF RZS  reference scope

 Photos

Scope

 Custom Commercial Carpet
Area 4: Scrape and patch exterior stucco then paint. Repair brownstone foundation walls. Extensive repair to brownstone at front entry. Acoustic insulation and new gypsum wall board framed into opening between office and administrative area. Anthropology 281 High St ACAD RZS    May 25, 2016

 Photos

Scope

 Signature Construction Group
Area 2: Paint exterior window trim, replace front and rear entry porch and stair systems Student WF 105 Cross St SLF-WF RZS    May 25, 2016

 Photos

Scope

 The Rockfall Company
Area 4: Vinyl side exterior,metal wrap exterior trim, paint exposed surfaces.  Vinyl side garage  and replace garage roof. New concrete entrance landing. University Relations 110 Mt Vernon ADM RZS    May 24, 2016

 Photos/Scope

Scope

 Superior Finishes
Area 2: Vinyl side exterior, metal wrap window trim, carpentry repair, concrete repair. Roof replacement. Student WF 64 Fountain Ave SLF-WF RZS    May 25, 2016

 Photos

Scope

 The Rockfall Company
Area 2: Paint exterior window trim, replace front and rear entry porches and stair systems Student WF 107 Cross St SLF-WF RZS    May 25, 2016

 Photos

Scope

 Signature Construction Group
Area 2: Vinyl side exterior, install new insulated windows; insulate window pockets, wrap exterior window trim with rolled metal, paint interior window trim completely. Student WF 223 Pine St - 2 bedroom SLF-WF RZS    May 25, 2016

 Photos

Scope

 CSS Morello
Area 1: Replace exterior wood siding. New insulated glass windows. Replace east and west porches. New roof over new east porch. Paint exterior exposed surfaces. Faculty/Staff 214 High Street SLF-WF RZS/WN    May 25, 2016

 Photos

Scope

 Signature Construction Group
Area 6: Steel repairs and replacement of deterioriated materials. Welding required. Prep, prime and paint entire fire escape. 6 building locations. Total of 8 fire escapes..

Fisk Hall

South College

Romance Languages

200 High St

190High St

200 Church St

262 High St

229 High St

300 High St (included in GC package)

200 High St

190 High St

200 Church St

ACAD RZS    May 23, 2016 Fire Escape Assessment and Scope Repair Report

Superior Finishes

Superior Finishes

Supeior Finishes

 

SIFCO, Inc

SIFCO, Inc

Superior Finishes

Area 1: CFA Music Studios Acoustic Door Installation CFA F 297 Washington Terracer ACAD RZS

May 24, 2016

OR

July 28, 2016

Scope

Signage

 

Aresco Construction

Quietstar Industries

Area 1: CFA Rehearsal Hall Acoustic Door Installation CFA A 60 Wyllys Ave ACAD RZS July 28, 2016

Photos/Scope

 

Aresco Construction

Quietstar Industries

Area 8: Replace exterior skylight above interior skylight. Provide new roof curb. Flash into existing metal roof.

DAC/Alsop House

301 High St

ACAD

RZS

Upon award.

Install: July 22, 2016 - August 20, 2016

Photos

Scope

 

Eagle Rivet

Roof Replacements: Area 8

125 Cross St

Exley lower roof over Pi Cafe' (managed by A Rubacha)

156 High St canopies

Alsop Carriage House Roof

Freeman Athletic Center Cross St Lobby Roof

CFA L Art Workshop Roof Replacement

Reference General Contractor Scopes in Areas 1, 2, 3, 4, 5 for additional roof work

125 Cross St

Exley lower roof

156 High St canopies

Alsop Carriage House Roof

Freeman Athletic Center Cross St Lobby Roof

CFA L Roof Replacement

RZS/AR

  Varies

64 Fountain Ave - see Area 2

125 Cross St Photos / Scope

22 Lawn Ave - see Area 1

156 High St Canopies Photos / Scope

Alsop Carriage House Photos / Scope

FAC Center St Lobby Roof Photos / Scope

CFA LRoof Photos / Scope

Macri Roofing

Macri Roofing

Superior Finishes

Macri Roofing

 

Macri Roofing

 

FJ Dahill Co.

Area 8: Replace roofing, gutters and downspouts, reflash chimneys.  Repair & repoint chimney where needed. Repoint masonry at southeast elevation
Court St Apts 272-278 Court St RP RZS   May 25, 2016

Photos

Scope

Eagle Rivet
Area 4: Install insulated glass windows, install new azek exterior stops. Paint interior window trim. Minor renovation to 1st floor east bathroom and 2nd floor west kitchen to accommodate window installation. Graduate Housing 258 Court St

RP

RZS

May 25, 2016

Photos

Scope

Signature Construction Group
Caulk exterior elevations identified. Hall Atwater 52 Lawn Ave

ACAD

AW

  May 24, 2016 Photos TBD
Area 3: Window replacement in Bedroom #1 Student WF 82 Lawn Ave SLF-WF RZS May 25, 2016

Photos

Scope

Signature Construction Group
Foss Hill Drive Line Striping Foss Hill Drive RB Completed Foss Hill Line Striping DeRita Construction
ACCESSIBILITY PROJECTS
Area 7: Accessibility upgrades to Van Vleck Observatory. The project consists of the design of accessible parking spaces, accessible ramped sidewalk leading to a new entry platform and new accessible toilet room located on the first floor of the observatory. Van Vleck Observatory 96 Foss Hill Drive ACAD RZS reference scope

Site Plan

Sitework Bid Documents

Interior ADA Renovation

REFERENCE SITEWORK BID DOCUMENTS FOR ADDITIONAL INTERIOR WORK.

Noyes Vogt Architects - Design

Aresco Construction - Restroom

Raccio Construction - Site

Area 1: Replace existing wood ramp with composite materials. (part of exterior project) 167 High St 167 High St ACAD / ADM RZS   May 23, 2016 Photos Signature Construction Group
Area 7 & Area 4: Restripe parking  lot and relocated current ADA parking space and access aisle to east entry door.

Demolish existing sloped sidewalk and provide new sloped sidewalk with 5’-0” turning radius landing. Install auto door opener tied into card access.

Romance Languages 300 High St ACAD RZS   May 23, 2016

Photos

Scope - ADA / Drainage

Raccio Construction


AR=Alan Rubacha arubacha@wesleyan.edu

ASW=Angela Wong aswong@wesleyan.edu

BH=Brandi Hood bhood@wesleyan.edu

MC=Mike Conte mconte@wesleyan.edu

RB=Rob Borman rborman@wesleyan.edu

RZS=Roseann Sillasen rsillasen@wesleyan.edu

TP=Tom Policki tpolicki@wesleyan.edu

ACAD=Academic    Admin=Administrative    Infra=Infrastructure    RP=Rental Properties    SLF=Student Life Facilities   SLF-WF=Student Life Facilities-Woodframes     ATH=Athletics

CPP=Central Power Plant    AAF=Academic & Administrative Affairs    MH=Manhole    DDC=Direct Digital Controls    GFI=Ground Fault Interrupt   SW=southwest    ADA=Americans with Disabilities Act

CFA=Center for the Arts 

Mandatory prebid conferences and walks will be scheduled the weeks of 2/29/16 and 3/7/16. Most walkthroughs will be in the afternoon.  Proposal forms will be uploaded and Addenda will be posted to this website after the walkthroughs.

MANDATORY PRE-BID CONFERENCES

 ALL PREBID MEETINGS BEGIN IN THE CADY BUILDING - 170 LONG LANE - MIDDLETOWN, CT - CONFERENCE ROOM A

 PROJECTS WILL BE AWARDED INDIVIDUALLY.

March 1, 2016 – 11:00 am: Area #4

  • 327 High Street: Window replacement for new FCU installation
  • 74 Wyllys Avenue: Vinyl siding/Carpentry
  • 230 Washington Street: Windows/Exterior paint/Porch replacement
  • 330 High Street: Windows/Vinyl siding/Roof replacement
  • 240 Court Street: Window replacement/Exterior siding/Apt 1 entry replacement/Apt 5 steel fire escape replacement
  • 300 High Street: Exterior wood trim repairs/Exterior paint
  • 281 High Street: Exterior paint/Brownstone repairs
  • 110 Mt Vernon: Vinyl siding/Replace concrete-masonry entry
  • 258 Court Street: Window replacement/Interior window trim painting

 

March 2, 2016 – 2:00 pm: Area #6

  • 262 High Street (Fisk Hall): Steel fire escape repairs & paint
  • 229 High Street (South College): Steel fire escape repairs & paint
  • 190 High Street: Steel fire escape repairs & touch up paint
  • 200 High Street: Steel fire escape repairs & touch up paint
  • 300 High Street: Steel fire escape repairs & paint
  • 200 Church Street: Steel fire escape repairs & touch up paint

 

March 3, 2016 – 2:00 pm: Area #7

  • Van Vleck Observatory: Accessible ramped sidewalk/Parking
  • 300 High Street: Accessible walk entry/Restripe parking lot/Site grading & drainage installation

 

March 7, 2016 – 10:00 am: Area #1

  • 151 Church Street: Bathroom renovations/Window replacement/Porch replacements/Wood stair tower repairs/New steel fire escape installation/Floor finishing/Interior painting
  • 16 Jackson Street: New stucco exterior finish/Window replacement (partial)/Carpentry
  • 22 Lawn Avenue: Window replacement/Vinyl siding/Carpentry/Roof replacement
  • 167/169 High Street: Window replacement-2nd floor/Fiber cement exterior/Carpentry/Exterior painting/Accessible ramp replacement
  • 154 Church Street: Repoint masonry exterior/Porch replacement/Kitchen counter replacement/ Screen wood floors/Interior painting/Bilco hatchway
  • 159 High Street: Vinyl siding/Porch replacements/Carpentry/Exterior Paint/Bilco hatchway
  • 162 Church Street: Garage repairs/Exterior paint
  • 214 High Street: Window replacement/Fiber cement exterior/Carpentry/Porch replacements/ Exterior paint/Portico roof replacement
  • CFA Music Studio: Acoustic door replacement/Paint/Carpet (2 rooms)
  • CFA Rehearsal Hall 003: Acoustic door replacement/Paint

 

March 7, 2016 – 2:30 pm: Area #2

  • 9 Vine Street: Window replacement/Vinyl siding/Porch ReplacementKitchen cabinet stain-varnish-repair/New flooring/Bathroom renovations
  • 12 Warren Street: Vinyl siding/Carpentry/Paint
  • 235 Pine Street: Window replacement/Porch replacements/Floor finishing/Interior-exterior painting
  • 113 Cross Street: Kitchen/bathroom renovations/Floor finishing/Interior paint/Electrical/Fire Alarm installation
  • 105 Cross Street: Exterior paint/Porch replacements
  • 64 Fountain Avenue: Vinyl siding/Carpentry/Concrete repairs/Exterior lighting/Roof replacement
  • 107 Cross Street: Exterior paint/Porch replacements
  • 223 Pine Street: Window replacement/Vinyl siding/Paint interior window trim

 

March 8, 2016 – 10:30 am: Area #3

  • 73 A/B Lawn Avenue: Window replacement/Vinyl siding/Carpentry repair/Interior window trim paint/Exterior paint/Exterior electrical
  • 37 Home Avenue: Window replacement/Vinyl siding/Porch replacement/Kitchen & bathroom renovations/Interior-exterior painting/Carpentry/Electrical
  • 55 Home Avenue: Kitchen & bathroom renovations/Carpentry/Floor finishing/Interior paint
  • 49 Home Avenue: Vinyl siding/Porch decking replacement/Carpentry/Kitchen & bathroom renovations/Floor finishing/Interior paint/Electrical
  • 27 Brainerd Avenue: Porch replacement/Railings/Exterior paint
  • 82 Lawn Avenue: Window replacement, first floor bedroom

 

March 9, 2016 – 1:30 pm: Area #5

  • 284 High Street: Replace plaster wall in basement kitchen/Scrape, prep & paint interior stone wall in mechanical space
  • 350 High Street (Russell House): Carpet replacement/Custodial closet floor replacement/Ceiling repair
  • Foss Hill 3: Bedroom flooring replacement
  • Van Vleck Observatory: Bathroom renovation for accessibility/Door hold open installation/ Automatic door opener

 

March 10, 2016 – 9:30 am: Area #8

  • 125 Cross Street: Roof replacement
  • 156 High Street: Concrete canopies roof replacement
  • 301 High Street (Alsop House): Skylight replacement
  • 301 High Street (Carriage House): Roof/cupola replacement
  • Freeman Athletic Center Cross Street Entrance: Roof replacement
  • CFA L (Art Work Shops): Roof replacement
  • 272-278 Court Street Apartments: Roof Replacement
  • CHECK PROJECT SCOPES FOR ADDITIONAL ROOFING